The project includes the construction of a 23m diameter open top round tank. The 6.8m high walls were formed using Peri's Rundflex forming system. Materials were hoisted with a 35m Self Erect Crane supplied by Mega Crane.

Location:
Saskatoon, SK

Owner:
Ostara Nutrient Recovery Tech

General Contractor:
Maple Reinders Inc.

Consultant:
Stantec Consulting Ltd.

Dates:
November 2011 – February 2012

Volume of Concrete Placed:
455 m³