The project includes the construction of a new Solids Contact Unit, Solids Contact Unit Sludge Tank, Waste Tank, Future Storage Tank, Chlorine Contact Tank and a Pump Well. It also included a new electrical room and chemical room. The project was an addition to the existing structure. Attention to detail was important as the work consisted of numerous tanks of varying sizes built at different elevations.
Location:
Westlock, Alberta
Owner:
Westlock Regional Water Services Commission
General Contractor:
Chandos Construction
Consultant:
ISL Engineering
Dates:
July 2009 – December 2009
Volume of Concrete Placed: